CONSULTANCY EXPERTISE IN POWER SECTOR

Neyveli Lignite Corporation has excellent technical skills in consultancy services for the renovation of old Power Stations. The details below depicts its experience in carrying out the Life Extension of 600MW Thermal Power Station. For further details to have such services in Renovation of old Power Stations send in your enquiries to the following address:

      Director/Power,
      CorporateOffice,
      Block-1,
      Neyveli-607 801.

Through Life Extension of Power station there is an advantage of early recovering of the plants compared to going in for New Installation. By Life Extension of Plant in a scientific and Methodical way the expenditure involved may be only 10 % compared to going in for a New Plant. The advantages of LEP are many

  • Increased Capacity
  • Improved Efficiency
  • Lower O&M equipment
  • Lower Emmission
  • Better reliability
  • And ... so on
LIFE EXTENSION

PROGRAMME OF THERMAL POWER STATION-I

Unit No.1 (50 MW) and Unit No.9 (100 MW) were shutdown on 1.4.1992 and 31.3.1992 respectively. Life Extension works in these two units 1 & 9 were taken up in June'92 in phase-I. After completion of LEP works, Unit-1 (50 MW) and Unit-9 (100 MW) were recommissioned in July'94 and November'94 respectively.
In Phase-II Unit 2 was released for LEP works in April'95 and re-commissioned in May'96. Unit-8 (100 MW) was released for LEP works in November'95and was recommissioned with Boiler 8B on 04.10.96. Boiler 8A was paralleled with 8B on 15.11.96. Unit-4 (50 MW) was released for LEP works on 3rd Aug'96 and was recommissioned on 12.07.97. Unit-7 (100 MW) was released for LEP works on 01.12.96 and was recommissioned with boiler 7B on 20.10.97 and boiler 7A was paralleled with boiler 7B on 28.03.98. Unit-3 was released for LEP works on 19.09.97 and recommissioned on 23.06.98.
Unit-5 (50 MW) was released for LEP works on 06.01.98 and recommissioned on 18.10.98. The Last Unit (Unit6 - 50 MW) was released for LEP works on 30.07.98 and works completed on 30.03.99. Thus the LEP of total 600 MW in TPS-I has been completed in March '99.

 
   