|
MINE - I
| MINE - IA
| MINE - II
| |
|
|
In February, 1978 Government of India sanctioned the Second Lignite Mine of capacity 4.7 MT of lignite per annum
and in February 1983, Government of India sanctioned the expansion of Second Mine capacity from 4.7 Million Tonnes
to 10.5 Million Tonnes. Further capacity expansion to 15 MT/A was sanctioned by Government of India in October 2004
and is presently under implementation.Unlike Mine-I, Mine-II had to face problems in the excavation of sticky clayey
soil during initial stage. The method of mining and equipment used are similar to that of Mine-I.
This Mine is located 5 kms south of Mine-I, spread over an area of 26 sq.kms. with 390 million tonnes reserves.
The initial mine cut was started in April 1981. The lignite seam was first exposed in September 1984 and regular
lignite mining commenced from March 1985. The overburden thickness varies from 50-100 m and the lignite thickness
varies from 8 to 22m. The average overburden to lignite ratio is 5m3 to a tonne. The lignite production in this mine
meet the fuel requirements of Thermal Power Station-II. The method of mining and equipment used are similar to that
of Mine-I.
|
|
|
|
|
The seam is the same as of Mine-I and is
contiguous to it. The lignite seam in Mine-II was first exposed
in September 1984 and the excavation of lignite commenced
in March, 1985. The Last overburden system (surface bench
system) under the expansion scheme was commissioned on 15.12.1991.
The lignite excavated from Mine-II meets the fuel requirements
of Thermal Power Station-II.
|
| |
|
Mine II |
| Selected Mining Area |
41.22 Sq.KM |
| Lignite Reserve |
624 M.T |
| Thickness Of Overburden |
45 to 103 Metres |
| Thickness Of Lignite |
8 to 22 Metres |
| Project Sanctioned |
22.02.1978 |
| Cost Of The Project |
Rs. 278 Crores |
| Project Inaugurated |
July 1979 |
| Project Commenced |
14.04.1981 |
| Initial Mine Cut Completed |
16.06.1985 |
| Lignite First Exposed On |
30.09.1984 |
| FIRST EXPANSION FROM 4.7 MTA to
10.5 MTA |
|
| Project Sanctioned For 10.5 M.T Stage |
February 1983 |
| Revised Cost Of Expansion |
Rs.1065.40 Crores : (Feb.'91) |
| Project sanctioned for 15.0 M.T Stage |
October 2004 |
Sl.No. |
Equipment |
Capacity |
Mine-II |
| 1 |
Bucket Wheel Excavator (BWE) Bridge Type |
1400 L |
3 |
| 2 |
BWE (Normal Type) |
1400 L |
2 |
| 3 |
BWE |
|
|
| 3.a |
a) with deep cut facility |
700 L |
2 |
| 3.b |
b) without deep cut facility |
700 L |
4 |
| 4 |
Mobile Transfer Conveyor |
11,000 tph |
2 |
| 5 |
Mobile Transfer Conveyor |
4,700 tph |
2 |
| 6 |
Spreader |
20, 000 tph |
2 |
| 7 |
Spreader |
11, 000 tph |
2 |
| 8 |
Tripper Car |
20, 000 tph |
2 |
| 9 |
Tripper Car |
11, 000 tph |
2 |
| 10 |
Stacker (Rail Mounted) |
|
1 (at TPS-II) |
| 11 |
Reclaimer |
2, 700 tph |
2 (at TPS-II) |
Width |
Type of Belt |
Length in Km |
No. of drive heads
and total capacity |
| 1800 mm |
Steel Cord |
4.86 |
4 Nos.(11 x 350 KW) |
| 2000 mm |
Steel Cord |
20.41 |
29 Nos.(52 x 630 KW) |
| 2400 mm |
Steel Cord |
20.56 |
14 Nos.(53 x 1250 KW) |